Everynameistaken
Structural
Hi All,
I have a question about the pour sequence of a reinforced concrete reservoir tank.
We have completed quite a few of these over the recent past and I am looking for ways and opinions from people in industry to try and make sure we are state of the art and efficient in our designs and construction sequencing.
Typically we design these structure per the CSA A23.3 (Canada) for the strength requirements and then employ the Eurocode rational approach for checking the reinforcing for the a service case of crack control. This approach almost always adds flexural bars to reduce the bar stresses and the size and spacing of the calculated crack widths per Eurocode. The we are now almost always adding Xypex or the like as a self healing additive.
My question comes relating to the pour sequence and potential timing delays between adjacent pours, since we try and use a state-of-the-art design procedure I want to make sure our construction methodology side is also meets the same standards.
In the past we used to use a checkerboard approach with adjacent pours having to be min 14 days apart. We have moved away from this to a strip model where our foundations slabs are usually in 3 strips with again adjacent pours having 14 days between. Then we build the reservoir in these three strips including the walls and the roof slab, all with 14 days between adjacent pours. This often leads to the two outside strips being poured on day 1 and the middle strip being poured on day 15.
I am looking for advice on this methodology, do people agree?
is 14 days to long?
Should we be pouring the base slab all fun one shot and letting it shrink as one entity?
should we pour strip1, then 2 then 3, but with less or no restriction on timing?
Another thoughts from people out there would be much appreciated.
I have a question about the pour sequence of a reinforced concrete reservoir tank.
We have completed quite a few of these over the recent past and I am looking for ways and opinions from people in industry to try and make sure we are state of the art and efficient in our designs and construction sequencing.
Typically we design these structure per the CSA A23.3 (Canada) for the strength requirements and then employ the Eurocode rational approach for checking the reinforcing for the a service case of crack control. This approach almost always adds flexural bars to reduce the bar stresses and the size and spacing of the calculated crack widths per Eurocode. The we are now almost always adding Xypex or the like as a self healing additive.
My question comes relating to the pour sequence and potential timing delays between adjacent pours, since we try and use a state-of-the-art design procedure I want to make sure our construction methodology side is also meets the same standards.
In the past we used to use a checkerboard approach with adjacent pours having to be min 14 days apart. We have moved away from this to a strip model where our foundations slabs are usually in 3 strips with again adjacent pours having 14 days between. Then we build the reservoir in these three strips including the walls and the roof slab, all with 14 days between adjacent pours. This often leads to the two outside strips being poured on day 1 and the middle strip being poured on day 15.
I am looking for advice on this methodology, do people agree?
is 14 days to long?
Should we be pouring the base slab all fun one shot and letting it shrink as one entity?
should we pour strip1, then 2 then 3, but with less or no restriction on timing?
Another thoughts from people out there would be much appreciated.