Do you require Concrete Rebar Placement Drawings/Shop drawings for every job? If not, when do you make the requirement necessary.
I have a contractor saying he never has had to submit these. Even though this is a relatively simple building concrete wise, we have a number of embeds on the project and required them. I told him he needed to submit them because they were required as part of the specs and drawings, but now he is going to the Owner and Arch saying we are adding un-neccesary costs to the job.
What are your typical practices?
I have a contractor saying he never has had to submit these. Even though this is a relatively simple building concrete wise, we have a number of embeds on the project and required them. I told him he needed to submit them because they were required as part of the specs and drawings, but now he is going to the Owner and Arch saying we are adding un-neccesary costs to the job.