4wilmar
Civil/Environmental
- Jan 21, 2006
- 30
As part of the on site QC team, I am concerned about thermal cracking in some up-coming pile cap pours which are over 10 ft thick, 15 ft wide and 20 ft long. However the designers have declared that these are not really mass concrete pours and no speacial precations need to be taken.
1. If none of the vertical faces are reinforced, does anyone know how much cracking we might expect if we start off with a concrete temp. of about 90 degrees.
2. If some of the piles are designated as tension piles, how will the tensile load transfer thru the pile cap to the column above without any vertical steel???
Any comments would be helpful as the contractor & engineer of record don't seem very concerned about any of this.
1. If none of the vertical faces are reinforced, does anyone know how much cracking we might expect if we start off with a concrete temp. of about 90 degrees.
2. If some of the piles are designated as tension piles, how will the tensile load transfer thru the pile cap to the column above without any vertical steel???
Any comments would be helpful as the contractor & engineer of record don't seem very concerned about any of this.