bookowski
Structural
- Aug 29, 2010
- 983
What is the preferred pour sequence/joint location for r/c link beams (beams linking shearwalls/cores). I am not referring to very large diagonally reinforced link beams, but the smaller traditionally reinforced type. Typically walls & columns are poured to underside of slabs and/or beams, then the slabs/beams, then again with walls/columns. With link beams this would create a joint at the slab depth below t.o.beam. It seems like there are the following options:
- Pour full link beams, leaving a ledge at sides with dowels out for the slab - you'd get a slab joint/crack along the beam.
- Block out the wall at the link beam including some depth back into the wall - this seems difficult to leave all the proper splices projecting
- Stop at b.o.slab and design all link beams as if they are shorter, thereby discounting the slab running over the top (reinf/ties could be held low as well). I've seen a variant of this detail where the link beam is held 2" low and the slab is poured thin over the beam - not sure if that is a good detail or not.
- Stop the entire wall low and then pour the upper wall + link beam + slab, this one would be a tough sell to the contractor.
- Pour full link beams, leaving a ledge at sides with dowels out for the slab - you'd get a slab joint/crack along the beam.
- Block out the wall at the link beam including some depth back into the wall - this seems difficult to leave all the proper splices projecting
- Stop at b.o.slab and design all link beams as if they are shorter, thereby discounting the slab running over the top (reinf/ties could be held low as well). I've seen a variant of this detail where the link beam is held 2" low and the slab is poured thin over the beam - not sure if that is a good detail or not.
- Stop the entire wall low and then pour the upper wall + link beam + slab, this one would be a tough sell to the contractor.