Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Concrete Joint Spacing

Status
Not open for further replies.

DCBII

Structural
Apr 15, 2010
187
There have been several discussions related to this, but they seem to be targeted to very specific situations. I want to have a more general discussion with other engineers on this. Thanks for your thoughts in advance.

Q1: For conventionally reinforced slabs/mats (water-bearing - or not if you've never done water-bearing), what's the largest distance between control joints you're willing to go, assuming the reinforcement ratio is at least 0.005? Why?
Q2: How about at even higher ratios?
Q3: What types of joints do you use?
Q4: What's the largest single placement you've done? How did it go? What were the parameters (e.g. reinf. ratio)?

So we're all on the same page regarding definitions:
-Control joints: any of the joints described below.
-Movement joints: Expansion or contraction joints as described below.
-Expansion joints: no reinforcement continues through the joint - meant to allow for thermal expansion
-Full contraction joints: no reinforcement continues through the joint - meant to control shrinkage cracking
-Partial contraction joints: 50% or less reinforcement continues through the joint - meant to control shrinkage cracking
-Construction joints: all reinforcement continues through the joint - provided for the contractor's convenience and/or to limit placement size
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor