Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations TugboatEng on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Composite beams 2

Status
Not open for further replies.

WWTEng

Structural
Joined
Nov 2, 2011
Messages
391
Location
US
I am working on my first major project with composite beams. I am designing the structure as unshored. But I have some questions in my mind and I am hoping to get some input on this forum. For example,

1) What is the approximate cost of placing studs over the beam?
2) My understanding is that 3/4" is the only recommended size for use as stud per AISC 350. Is that correct?
3) I understand that the studs should project a min of 2" above the deck rib and that there should be at least 2" concrete cover over the stud. Correct?
 
1) I imagine the answer to this question will depend on where you are. I use a value of $2.00-$3.00/stud installed

2) I have always used 3/4" dia studs and I don't see why you couldn't use smaller. I do not have ASIC 350 in front of me so I can't really comment.

3) According to the AISC studs are required to be placed 1-1/2" above the deck and 1/2" below the top of slab. This basically correlates to every composite deck catalog I have seen that requires 2" of cover above the flutes.
 
Ref AISC 360-05 specifications:
2) stud shear connectors 3/4" or less in diameter. You could also use channels.
3) After installation studs shall extend not less than 1 1/2" above the top of the steel deck and there shall be at least 1/2" of concrete cover above the top of the installed studs.
 
Thanks for the input. The 1/2" clear cover over the stud is something I wasn't clear on. I thought it was supposed to be 2".
 
Another question: Is it more practical to have uniform stud layout rather then freeform, and how common is it to use non-uniform layout?
 
Freeform?

Usually the studs are spaced evenly. The only time I have seen them not spaced evenly is in regards to girders where you will have different stud counts between the locations of the point loads.... ie a girder with point loads at the 1/3 points may have an (18) (5) (18) pattern. Even the studs are spaced evenly between the point loads.
 
Steel, thanks. By freeform, I meant non-uniform layout. And yes my question was in regards to a girder where I have two point loads at 3rd points, and I was wondering if I could use a stud arrangement of say 18, 4, 18.

And now I have another question. I understand that the recommended minimum composite action is 50% (base on some articles I read online). But I have some beams where the composite action is around 30-40%. what are some of the problems I could expect with a low composite action such as this.

 
No offense, but all of this stuff is answered in the AISC Specification and Commentary for Chapter I as well as the associated design examples, all of which are available on AISC's website for free...
 
As Willis suggests, all of this information can be found in the manual. Either in the specific chapter or the commentary.

With regards to the % composite action. AISC used to require a minimum 25% composite action (I believe) but they have removed that requirement for the 13th edition. I don't know about the 14th edition as I do not own one. I thought the commentary specifically addressed the removal of this limit and why they went in this direction.
 
Willi, Steel. Thanks.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top