Jul 9, 2007 #1 ppmsb Mechanical Joined Jul 6, 2007 Messages 29 Location MY Hi, We are going to commission a 25MW condensing STG soon. Any experience to share ppm
Jul 9, 2007 #2 byrdj Mechanical Joined May 21, 2003 Messages 1,663 Location US On the turbine side; Back up lube oil, Emergancy governor, Casing drains Primary speed control and Push button trip are operational. On the generator side; voltage regulator and breaker phasing Upvote 0 Downvote
On the turbine side; Back up lube oil, Emergancy governor, Casing drains Primary speed control and Push button trip are operational. On the generator side; voltage regulator and breaker phasing
Jul 10, 2007 #3 GTstartup Electrical Joined Mar 5, 2005 Messages 422 Location US Yeah, shell out the OEM commissioning engineer Upvote 0 Downvote