Dik,
Yes, you could do this with rigid links in RISA. The way I do it is setting the one beam center line at zero and then setting the other beam center line at plus 14 in your case. Then adding fixed rigid links between them at like a 1 foot interval. I am assuming there could be another way, but one of the RISA guys will have to respond to you. Hope this helps.
Scott.