Faisal0088
Civil/Environmental
Hi,
Few days back I have designed a 7 storied RCC building combined foundation. In my design I did consider soil BC 4Ksf. C1 and C2 each P= 278 Kip. The size was 19.5'x7.5'.
My problem is, during construction the client did not follow my design. They reduced the size of the footing. Its now 17'x5' !!! . I have re analyzed the soil pressure it seems 6Ksf above!!!. I have told them to demolish that. Still they are asking me to let them to connect MS Bar and Extend the edge as per my early design.
Whats the solution for such case. Will it be appropriate to connect MS Bar and cast RCC along the edge? Will it work as like a homogeneous foundation?
Please some one help me! Looking forward to hear from my Engr fellows around the world.
Thanks
Few days back I have designed a 7 storied RCC building combined foundation. In my design I did consider soil BC 4Ksf. C1 and C2 each P= 278 Kip. The size was 19.5'x7.5'.
My problem is, during construction the client did not follow my design. They reduced the size of the footing. Its now 17'x5' !!! . I have re analyzed the soil pressure it seems 6Ksf above!!!. I have told them to demolish that. Still they are asking me to let them to connect MS Bar and Extend the edge as per my early design.
Whats the solution for such case. Will it be appropriate to connect MS Bar and cast RCC along the edge? Will it work as like a homogeneous foundation?
Please some one help me! Looking forward to hear from my Engr fellows around the world.
Thanks