Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Climbing Core-Floor connections

Status
Not open for further replies.

hanihafiz

Structural
Jun 21, 2011
13
We are constructing a project where construction of building cores will proceed prior to construction of connected floor beams and slabs. Bars with couplers shall be provided at the locations of connected reinforcement. The designer said that there is no other precaution to be followed at these connections. Is this true? In some cases, we have connected elements of 12.0m spans. Depending on shear friction in this case for shear resistance, is it a wise decision?
 
Replies continue below

Recommended for you

No. Connections to the cores should be rebated into the walls. Proprietary systems are normally used, which are called 'reboxes' or variations thereof.
 
Thanks hokie66. can you direct me to reference to site or document of that system?
 