I have a long and skinny billets building with cmu walls and wood trusses spaced at 2 ft o.c. Please see the attached drawing and details. There is a 3500 pound chord force that I would like to transfer into the bond beam at the top of the cmu shear wall. There is about a 4'-0" elevation difference between the top of the roof sheathing and the top of the shear wall. I have detailed truss blocking panels running between the main roof trusses to transfer the chord force into the shear wall. The question I have is; does each blocking panel and the connections to and from the blocking panels have to be designed to take the 3500 pound force or do all of the blocking panels share in transferring the 3500 pound chord force into the shear wall?
I appreciate any help or guidance you can give me. Please feel free to comment on anything I have detailed too. Thanks!