Changing overall end date

Status
Not open for further replies.

Karen23

Computer
Joined
Mar 7, 2003
Messages
1
Location
GB
I have tried changing the overall end date for a project; but because some tasks have been deleted which had an end date of 2004 for some reason the plan keeps jumping back to that date even though those tasks have been deleted. Can anyone please help me?
 
Have you tried to re-baseline? TTFN
 