1906
Chemical
- Jun 30, 2003
- 49
Hi, we started recycle gas comp. driven by high pressure steam turbine this july after coupling inspection and routine maintenance during turn-around period in our refinery hydrocracking unit. After start up, turbine side axial displacement(to active side) has been increasing step by step and recently almost reaching its trip set 0.6mm. Furthermore, recent trend shows comp. side axial displacement also increasing to inactive side, but lube oil analysis data and color is good condition, temperature of bearings are also in reasonable pigures. With this situation, we are on the verge of deciding somthing to do such as shutting down the unit or operating compressor more. So,If any body experienced something similar to our situation, please let me know.