I run a wood working manufacturing company. I am having difficulty getting Project to do what I need. Here is my example.
I need to cut 400 boards. I have a saw (resource) that can cut 10 boards an hour. I want to be able to put in this rate and have Project tell me that this task will take 40 hrs to complete. Or if I have a deadline of 20 hrs, that I need to employ a second saw to meet my deadline. Can this be done with Project?
Please help.
I need to cut 400 boards. I have a saw (resource) that can cut 10 boards an hour. I want to be able to put in this rate and have Project tell me that this task will take 40 hrs to complete. Or if I have a deadline of 20 hrs, that I need to employ a second saw to meet my deadline. Can this be done with Project?