Calendar Days

Status
Not open for further replies.

TonyLL

Electrical
Aug 21, 2002
2
I need to show columns for both "Work Days" and "Elapsed Days" (Calendar Days) for "Duration" for each Task on a Project schedule. Currently Duration shows "Work Days" -- How do I get "Elapsed Days" (Calendar Days) also?
Tony
 
Replies continue below

Recommended for you

2 options:
> copy start and finish columns to Excel and do the math there and copy into one of the user columns.

> VBA macro