Dec 14, 2006 #1 thegreatyoshi Civil/Environmental Joined Dec 14, 2006 Messages 2 Location GB my project was 64 days long. however i have changed some task durations but the software has not calculated a new project duration. how do i do this?
my project was 64 days long. however i have changed some task durations but the software has not calculated a new project duration. how do i do this?
Dec 14, 2006 #2 IRstuff Aerospace Joined Jun 3, 2002 Messages 44,895 Location US Unless the tasks are linked so that the overall duration is increased, there would be no increase in duration TTFN Upvote 0 Downvote
Unless the tasks are linked so that the overall duration is increased, there would be no increase in duration TTFN
Dec 15, 2006 Thread starter #3 thegreatyoshi Civil/Environmental Joined Dec 14, 2006 Messages 2 Location GB i know that but they ARE linked Upvote 0 Downvote
Dec 15, 2006 #4 IRstuff Aerospace Joined Jun 3, 2002 Messages 44,895 Location US Then the critical path isn't affected by your alterations. TTFN Upvote 0 Downvote
Dec 19, 2006 #5 tweiler Computer Joined Dec 19, 2006 Messages 2 Location CA Make sure you have auto-calculate turned on. Hit F9 to calculate if it isn't. Upvote 0 Downvote