Hi All,
Recently moving from the O&G industry into mining, so I have never done any calcs on conveyors / idlers.
I require some help with calculating the load on a centre roll of a suspended, 3 roll idler set. The reason why I want to do this is because I notice there is significant length of free belt between the suspended idlers and and the next carry idler along the conveyor.
Assumptions:
70% of total load on the centre roll
Friction = 0.9
Idlers have 45 deg trough angle
Some numbers I have:
belt running at fully loaded case: Q = 15,000 tph
Belt speed: v = 5.5 m/s
Belt tension: T = 520kN
Belt Mass: M = 80 kg/m
Distances between Suspended (Idler1) and inline (Idler2):
Vertical: Z = 0.382 m
Horizontal: X = 3.798 m
Distance centre-centre: 3.818 m
If someone could help me out / point me in the right direction, that would be greatly appreciated.
Thank you
Recently moving from the O&G industry into mining, so I have never done any calcs on conveyors / idlers.
I require some help with calculating the load on a centre roll of a suspended, 3 roll idler set. The reason why I want to do this is because I notice there is significant length of free belt between the suspended idlers and and the next carry idler along the conveyor.
Assumptions:
70% of total load on the centre roll
Friction = 0.9
Idlers have 45 deg trough angle
Some numbers I have:
belt running at fully loaded case: Q = 15,000 tph
Belt speed: v = 5.5 m/s
Belt tension: T = 520kN
Belt Mass: M = 80 kg/m
Distances between Suspended (Idler1) and inline (Idler2):
Vertical: Z = 0.382 m
Horizontal: X = 3.798 m
Distance centre-centre: 3.818 m
If someone could help me out / point me in the right direction, that would be greatly appreciated.
Thank you