I want to calculate the short circuit at my main switchboard.
I have the transformer's data (2MVA, 6%) and I have the network upstream fault so I use:
1 / MVA system = 1 / MVA utility + 1 / MVA transformer
I presume that's correct, right?
Only one more thing: for the utility they gave me the utility's earth fault kA not the 3 phase fault kA.
Is there a way to work out the utility's 3-phase fault kA from the single phase to earth fault kA they gave me and how?