Don't forget that the operator is not the only possible source of error. A crane can still be tipped while being operated entirely within the manufacturer's limits.
Detailed reasons for this sort of event are usually difficult to find, since they tend to be obscured by legal secrecy.
On a freeway construction job not so long ago near Melbourne, a crane tipped over into the adjacent creek. Rumour in the industry was that the crane lift had been carefully engineered, and piles driven at the four planned outrigger positions to provide the necessary foundation capacity. However, as it turned out the crane was not accurately positioned over the piles, and it tipped due to foundation failure.
I recall an occasion many years ago when a sub-contract crane erector was installing the machinery deck for a tower crane on the base of a floating concrete caisson (for final fitting out prior to floating to location some miles off the Queensland coast).
The sub-contractor was quite convinced that he knew the mass of the machinery deck. He also knew that it was at the maximum radius/capacity of the mobile crane that he was using for the lift. He happily directed the crane driver to jib out, with the load about 30 feet above the deck of the caisson.
Fortunately two experienced rigging foremen from the main contractors were monitoring the operation. When the two rear outriggers went slack in their housings (indicating that the mobile crane was right on the point of tipping about the remaining two outriggers), they stepped in and ordered the crane driver to jib in, and replace the load on the wharf from which they were working.
The subcontractor protested loudly (he had been aiming for a bonus for early completion), telling anyone within earshot that the crane would p... it in". He was instructed to weigh the load on the nearest weighbridge. When the foremen went to the weighbridge next morning they observed the water tank being drained, and reels of hoisting cables and other surplus items being removed from the load! (Subsequently the lift was successfully completed, but with the load limited to the items listed in the manufacturer's weights). Had that crane dropped its load onto the caisson, it would almost certainly have sunk it, with a probable cost of $10 million or more.