SueK
Mechanical
- Jul 13, 2012
- 3
I need to build a project schedule which includes enterprise level portions (no issues), and then a repetetive task list for each of 15 locations. Because the 15 locations are identical (for now), I'm trying to find a way to avoid buidling them individually.
I can easily copy and paste tasks and durations, but so far I can't figure out to get predecessors to be unique to each instance. If I export the generic version, when I import / append, all task link back to the original list, instead of to the new line items.
I tried buiding it in Excel and importing, but duration all came in as 1 day. I'm definetly spending too much time trying to avoid typing it all in, but I'm concerned if I manually build all these links, I risk errors.
Anyone know a robust method to do this?
I can easily copy and paste tasks and durations, but so far I can't figure out to get predecessors to be unique to each instance. If I export the generic version, when I import / append, all task link back to the original list, instead of to the new line items.
I tried buiding it in Excel and importing, but duration all came in as 1 day. I'm definetly spending too much time trying to avoid typing it all in, but I'm concerned if I manually build all these links, I risk errors.
Anyone know a robust method to do this?