- Jun 20, 2008
- 6
If a precast drive pile is broken I would normally have a pile driven either side and form a cap over the origional pile. A piling contractor recently had a broken pile and drove a new pile in tight to the origional (1No.).
As I see it I now need to check the foundations ground beam which is now longer and supporting a return ground beam at its end.
Are there any other issues I should be aware of?