josedipofi
Mechanical
- Jul 12, 2009
- 12
I have a question regarding bolts preload:
I calculated a flange according to appendix 2 of Asme VIII div.1, and now i have to define the max preload bolts to assemble the joint, i saw several calculations where is showed a pre stress of the bolts of 50% of the allowable stress.(this value is quite common between our vendor)
If i check the flange with that value, the stress of the flange&rigidity factor are too high.
My question is: the preload value to be used during assembly the joint must be checked/verified according to appendix 2 in any case or not? Looks that nobody do that, i mean that after calculating the flange almost no vendor check it against preload of the bolts
I calculated a flange according to appendix 2 of Asme VIII div.1, and now i have to define the max preload bolts to assemble the joint, i saw several calculations where is showed a pre stress of the bolts of 50% of the allowable stress.(this value is quite common between our vendor)
If i check the flange with that value, the stress of the flange&rigidity factor are too high.
My question is: the preload value to be used during assembly the joint must be checked/verified according to appendix 2 in any case or not? Looks that nobody do that, i mean that after calculating the flange almost no vendor check it against preload of the bolts