Regarding bolt calcs in EN 1993-1-8
Is the bolt tensile load F_t,Ed equal to total tensile load including preload or is it only applied load external to preload?
The question arises for the following reasons:
1. Notice the tensile resistance check F_t,Ed <= F_t,Rd. Where resistance is K_2*F_ub*A_s/gamma. If Preload is as suggested 0.7F_ub*A_s and K_2 = 0.63 and F_t includes pretension, then the check will always fail under preload alone since 0.63/gamma is less than 0.7.
2. Also notice that the cat C combined slip resistance has a factor equal to preload (F_p,C) minus 0.8F_t,Ed. This make sense if F_t,Ed does not include preload since larger seperating load descreases contact force on the friction plane. But if F_t,Ed includes preload, this factor is double dipping
3. From the first to observations, I would assume that F_t,Ed does not include preload and is exclusively external load. However, that would mean that the tensile checks are not conservative as overly preloading a bolt may exceed tensile capcity which should be checked but isn't explictly. Also F_t,Ed not including preload would mean that the punch shear restistance check F_t,Ed <= B_p,Rd would not be conservative as the total punch shear load would not be accounted for.

Overall there seems to be a contradiction. I see this contradiction resolved if F_t,Ed = max(preload ; external load) and the largest allowable preload was reduced for countersunk bolts. However, that is an assumption with no justification other than it resolves the contradiction (which I could be wrong about) and is not stated in the code.
 
Replies continue below

Recommended for you

Please don't double post

The problem with sloppy work is that the supply FAR EXCEEDS the demand
 