somarp
Mechanical
- Sep 14, 2004
- 7
I need some help - I am working on a new design. I will tell you that I am not an engineer, but just a mechanical designer so please understand the basics of my questions.
I am designing a carriage that is rack and pinion drive. The carriage is being driven by 2 planteries with 2 Eaton motors driving them. The planeties are developing 30,000 pounds of force - 15,000 per each side.
The are 2 racks that are welded to a 8" x 8" sqaure tube and the carriage pinions run along the outside of the rack.
I am installing 2 prox switches at the end of the travel at one end of the tube. The first is a slow down and the switch is a stop.
My question is - I am wanting to design some mechanical stops to install to the side of the rack at the end of the tube. The stops would be there if in the event of a failure of either prox which would probably result in damage to the rack system.
I am thinking about using 2 square bars - 2" think and drilling thru holes in them and then drilling and tapping the rack on each side. Therefore I would mount the bars with bolts on each side of the rack. So in the event of a switch failure each bar would potentially see 15,000 force being applied to them. I know to design the bolts to withstand the shear force, but I am curious do I need to address the clamp force of the hardware to withstand the 15,000 force. I am thinking that I need too, but am unsure how.
I would appreciate any help. Thanks in advance.
I am designing a carriage that is rack and pinion drive. The carriage is being driven by 2 planteries with 2 Eaton motors driving them. The planeties are developing 30,000 pounds of force - 15,000 per each side.
The are 2 racks that are welded to a 8" x 8" sqaure tube and the carriage pinions run along the outside of the rack.
I am installing 2 prox switches at the end of the travel at one end of the tube. The first is a slow down and the switch is a stop.
My question is - I am wanting to design some mechanical stops to install to the side of the rack at the end of the tube. The stops would be there if in the event of a failure of either prox which would probably result in damage to the rack system.
I am thinking about using 2 square bars - 2" think and drilling thru holes in them and then drilling and tapping the rack on each side. Therefore I would mount the bars with bolts on each side of the rack. So in the event of a switch failure each bar would potentially see 15,000 force being applied to them. I know to design the bolts to withstand the shear force, but I am curious do I need to address the clamp force of the hardware to withstand the 15,000 force. I am thinking that I need too, but am unsure how.
I would appreciate any help. Thanks in advance.