deeman
Civil/Environmental
- Aug 12, 2003
- 8
Is anyone aware of any regulations or rules of thumb on how close to existing underground pipelines blasting should be allowed. We have an existing 12" sewer force main which is about 8 feet from where a contractor is preparing to blast for a new 18" trunk sewer. The gravity sewer will be about 10 feet deep while the adjacent force main is 3 feet deep.