Einsteim
Structural
- Jan 10, 2008
- 76
See attached pictures - I am NOT the EOR for this project, but noticed a potential disaster waiting to happen. I rough calculated the point load from beam reaction to be in the 25-30 kip range from roof load, CMU wall DL, PC Plank DL-LL, no bearing plate installed on the CMU and I believe not grouted below and of course no column below either. The CMU has slight diagonal crack (maybe not clear on the picture). I feel this needs to be reported to Owner as a serious concern...thoughts?