fsck
Electrical
- Apr 27, 2010
- 105
I'm an EE helping a homeowner planning a new residence in CA. The property will be fed with 4160v/20A, and we'll have a grid-tie solar array, backup inverters & generator. The house will be fed with 208/Wye.
I'm trying to SWAG ideas & prices before he goes to the local PE for a legal design. The trouble is, while in decades past I've installed and repaired HV starters, witnessed HiPot tests, etc; I've never had to spec/cost switchgear/cable. So this is a new adventure to me; and I have some really likely elementary [to most of you] queries to help me get started.
a) We'll have a straight 1000' buried 4160v cable from the PGE meter/solar to the house. Is such usually put in Sch 40 pipe, direct buried in the trench or? What's code/practice on ditch sharing? Utilities I've observed seem to put telco/cable atop it with a foot or so of dirt standoff.
b) We want provision for a later 2nd cable; in case he builds a 2nd house. Where can I go to learn about pull lengths for such HV cable in conduit?
c) The utility will demand disconnects. What's the price differential for 4160 gear in interior vs outside cabinets? [They seem almost willing to have them within the solar building iffen they have their lock on the door...]
d) We'll need to not just disconnect from the utility but maybe also transfer to the generator. [I'm looking at several approaches.] Are double-throw center-off switches available at 4160/3ph, or will vendors think I'm crazy for even asking? (If not, I assume we can get mechanically-interlocked disconnects so only one can be closed at a time.) Suppliers to consult? How can such be run remotely: motor actuator, air cylinder....?
e) What else should I worry about...?
I'm trying to SWAG ideas & prices before he goes to the local PE for a legal design. The trouble is, while in decades past I've installed and repaired HV starters, witnessed HiPot tests, etc; I've never had to spec/cost switchgear/cable. So this is a new adventure to me; and I have some really likely elementary [to most of you] queries to help me get started.
a) We'll have a straight 1000' buried 4160v cable from the PGE meter/solar to the house. Is such usually put in Sch 40 pipe, direct buried in the trench or? What's code/practice on ditch sharing? Utilities I've observed seem to put telco/cable atop it with a foot or so of dirt standoff.
b) We want provision for a later 2nd cable; in case he builds a 2nd house. Where can I go to learn about pull lengths for such HV cable in conduit?
c) The utility will demand disconnects. What's the price differential for 4160 gear in interior vs outside cabinets? [They seem almost willing to have them within the solar building iffen they have their lock on the door...]
d) We'll need to not just disconnect from the utility but maybe also transfer to the generator. [I'm looking at several approaches.] Are double-throw center-off switches available at 4160/3ph, or will vendors think I'm crazy for even asking? (If not, I assume we can get mechanically-interlocked disconnects so only one can be closed at a time.) Suppliers to consult? How can such be run remotely: motor actuator, air cylinder....?
e) What else should I worry about...?