WWTEng
Structural
- Nov 2, 2011
- 391
Typically there is exp joint/bond break between slab-on-grade & bottom of the basement wall. Yet, the wall is assumed to be pinned at this location (not designed as cantilevered). Does this mean that the joint/bond break is assumed to be compressed to the point where the force is transferred into SOG?