Is it a common practice to show a louver and backpacking behind timber lagging in a soldier pile retention system? We specify to replace any lost soil behind the lagging before installation of the next board to have solid soil behind the lagging. I was told however that it should be backpacked with a drypack mixture and to provide a 1 1/2" louver between the boards and that my original detail was incorrect. Was my original detail showing the replaced soil wrong?