caissondriller
Geotechnical
- Jun 7, 2003
- 5
In loose sand and gravel {5-8-5 blows per six} we are advancing 42” steel pipe to 15 or 16 feet. After steel pipe is set permanent 36” corrugated pipe {CMP} is set. After 36” CMP is backfilled with existing drilled spoils, the 42” casing is extracted. A steel plate is set on the 36” CMP and vibrated with a plate tamper for approx 5 min. After vibrating any annular space is filled and CMP vibrated again. I have used this method on other projects with similar conditions, but I need to convince the field engineer this is a viable alternative to flow able fill. Any comments or suggestions appreciated.