ACE58
Structural
- Feb 13, 2006
- 28
A project currently under construction is steel framed with 8" bypass girts starting at 5'-4" above finished floor. From the floor to +5'-4" there is an 8" masonry wall with vertical #5 at 1'-4"c/c full height from the foundation. All cells are grouted full, full height. There is horizontal masonry joint reinforcing at 8"c/c full height, & bond beams with continuous(2)#5 with top elevations +2'-8" & +5'-4". On the exterior is an earth berm (assumed 45 psf equivalent fluid weight of soil) which extends to 4" below the top of masonry. The wall was designed with the aid of NCMA tables. There is a foundation drain & 1'-0" wide gravel extends from the foundation to 8" below the top of wall, full length of wall. The contractor will be starting to lay the masonry soon & wants to know how soon he can backfill after erection. If this were a reinforced concrete wall, I would tell him that after the concrete has reached its design strength (even if it's before 28 days)& the wall must be braced during compaction. I have looked through numerous masonry design manuals & have not found guidelines for when the backfilling behind a reinforced masonry wall may start. Can anyone point me to reference that covers this topic? Do I follow a similar route as if concrete & take grout samples to have them tested for design strength? Does grout gain strength on a similar curve to concrete? The contractor is behind schedule due to weather & is looking to cut time out of the schedule wherever he can. Thanks for any help you can provide.