Dear Sir:
The back pressure regulator located on the
nitrogen purge line (upstream pressure=10kg/cm2g)
open to relieve the pressure when the pressure upstream
increase above the set point.Upstream pressure regulators(
back pressure regulator) close upon loss of upstream pressure.
However, the downstream is vessel which OP=5kg/cm2g
Could you please help me how to determine the set pressure
for this PCV ?
Is PCV set pressure=3kg/cm2g or 6kg/cm2g will be most appropriate for this case?
Appreciate for your any comment and thank you very much.
The back pressure regulator located on the
nitrogen purge line (upstream pressure=10kg/cm2g)
open to relieve the pressure when the pressure upstream
increase above the set point.Upstream pressure regulators(
back pressure regulator) close upon loss of upstream pressure.
However, the downstream is vessel which OP=5kg/cm2g
Could you please help me how to determine the set pressure
for this PCV ?
Is PCV set pressure=3kg/cm2g or 6kg/cm2g will be most appropriate for this case?
Appreciate for your any comment and thank you very much.