Sirs:
For nonmetallic piping,Heat Fusion Bonds the ASME B31.3
Acceptance Criteria requires non unfilled and unbounded areas.OK.But wich is the MANDATORY examination that the
erector have to perform to accomplish this,in case that the
contract only indicates that the piping shall be according toB31.3?For metallic piping it seems that this point is clear,but not for nonmetallic pipelines.
Thanks for any comment on this,
Capablanca
For nonmetallic piping,Heat Fusion Bonds the ASME B31.3
Acceptance Criteria requires non unfilled and unbounded areas.OK.But wich is the MANDATORY examination that the
erector have to perform to accomplish this,in case that the
contract only indicates that the piping shall be according toB31.3?For metallic piping it seems that this point is clear,but not for nonmetallic pipelines.
Thanks for any comment on this,
Capablanca