Fr109
Structural
- Jul 15, 2008
- 3
Hi,
Not having a lot of experience, I'm looking for a simple approach for the following situation:
I need to design a prestressing bed foundation consisting of 2 parallel concrete walls 128 ft long, 8ft high x probably 16" thick, 7 ft apart. The walls will be buried up to 16" from the top on the outside, and 40" from the top in the center with compacted gravel/sand. Maybe considering a plain concrete floor in the center if necessary.
On top the walls, and perpendicular to them, is welded a light metal structure consisting of a 6" channel on edge, at 4 ft o.c. On top of these, in the center, running parallel to the walls is a plate 1/8" thick x 13" wide whose edges are supported by 4" channels on edge.
Loads: A moment at each end, tending to uplift the ends of the walls, 1,630,000 lbs-ft, situated at 13.5 ft from each end.
Plus a 243 kip axial load compressing towards the center, applied at the top of each wall also at 13.5 ft from each end.
QUESTION: Can these walls be considered as having continuous lateral bracing, so that I can provide reinforcement only for the uplifting moment, and not have to worry about the axial loading?
Any advice would be very much appreciated.
Thanks!
Not having a lot of experience, I'm looking for a simple approach for the following situation:
I need to design a prestressing bed foundation consisting of 2 parallel concrete walls 128 ft long, 8ft high x probably 16" thick, 7 ft apart. The walls will be buried up to 16" from the top on the outside, and 40" from the top in the center with compacted gravel/sand. Maybe considering a plain concrete floor in the center if necessary.
On top the walls, and perpendicular to them, is welded a light metal structure consisting of a 6" channel on edge, at 4 ft o.c. On top of these, in the center, running parallel to the walls is a plate 1/8" thick x 13" wide whose edges are supported by 4" channels on edge.
Loads: A moment at each end, tending to uplift the ends of the walls, 1,630,000 lbs-ft, situated at 13.5 ft from each end.
Plus a 243 kip axial load compressing towards the center, applied at the top of each wall also at 13.5 ft from each end.
QUESTION: Can these walls be considered as having continuous lateral bracing, so that I can provide reinforcement only for the uplifting moment, and not have to worry about the axial loading?
Any advice would be very much appreciated.
Thanks!