Thank you for the post.
I should have explained it more clearly.
We are a millwork manufacturing company. I have created my schedule with all tasks being individual, (handrails, stairs, shutters, etc.,), that have a date at which they must ship to be on-site “just in time”. That date may be weeks or months away; I can produce the product at any time before that must finish date. Because my production schedule changes constantly, I sometimes create gaps of one or two days. Most of my tasks are one to two day durations. What I would like is one of the tasks to “jump” into the open gap in my schedule automatically.
If the solution that you provided will achieve this, then disregard… I will try it and see what happens.
Best regards,
Mike