TDAA
Geotechnical
- Jul 28, 2005
- 600
Can someone tell me if this spec also covers the orientation of the perforations when the pipe is used for drain purposes?
We have a situation where a foundation drain is being installed. The arch/structural/civil, whomever has specified ASTM D2729. The submitials show the perfs down, and the spec says to install them up. Not looking for a debate on which way people think they should go, just wether there is any backup in the spec.
Thank you.
We have a situation where a foundation drain is being installed. The arch/structural/civil, whomever has specified ASTM D2729. The submitials show the perfs down, and the spec says to install them up. Not looking for a debate on which way people think they should go, just wether there is any backup in the spec.
Thank you.