tw
Structural
- May 30, 2001
- 70
This building has a 6.5" composite concrete deck (3500 psi, fiber-reinforced, 520 lb cement) that is the second floor of a 3 story building. There is no ground floor so below this deck is not conditioned space. It is covered by metal framing so it is protected from rain.
There was a problem with the terrazzo in first go round, now they want to put a Key EpoCoat epoxy resin to bond terrazzo to slab. Report done by a concrete testing company warns owner to get an ASR expert to comment on the possibility of ASR developing since top of slab will have limited vapor transmission.
Is it possible to pull enough moisture from unconditioned air through metal deck to concrete to get ASR in this case? I have never heard of anything like that.
There was a problem with the terrazzo in first go round, now they want to put a Key EpoCoat epoxy resin to bond terrazzo to slab. Report done by a concrete testing company warns owner to get an ASR expert to comment on the possibility of ASR developing since top of slab will have limited vapor transmission.
Is it possible to pull enough moisture from unconditioned air through metal deck to concrete to get ASR in this case? I have never heard of anything like that.