syagla, first you'd need to know the Code of Construction.
I'll ASSume Sec VIII, Div 1. You'd need to know the material. Then, based on the (governing, if applicable) thickness, exempt (or not) per the relevant Part: UCS, UHA, UNF, etc. Required thickness would not likely be needed unless applying UCS-66(b).
Regards,
Mike
The problem with sloppy work is that the supply FAR EXCEEDS the demand