ASME response to WRC 429

Status
Not open for further replies.

heaterguy

Mechanical
Nov 15, 2004
99
Did ASME make a published response to WRC 429?
 
Replies continue below

Recommended for you

No - ASME has not specifically (nor officially) endorsed nor refuted WRC 429.

My personal view is that it is "good engineering practise". That said, there is a non-mandatory appendix winding its way through the committees that incorporates the vast majority of WRC 429. As well, the Div. 2 Re-Write portion on stress linearization borrows heavily from WRC 429.

That said, if you talk to engineers who have been doing FEA for pressure vessels for 25+ years, they will tell you that the methodology explained in WRC 429 is what they used "long time ago" - linearizing at the component level and then calculating the stress intensity. Really, the only argument now is the placement of the SCLs (stress classification lines). In my experience, the disagreement arises between the nuclear guys whose reactors have "unique" geometries, and the non-nuclear, whose geometries are rather regular.

Are you getting push-back from a client or regulator about using WRC 429?
 
In that case, I would kindly refer the AI to the Foreword in Div 1 (I'm assuming that your application is Div 1), second paragraph, near the end:

"Accordingly, it is not intended that this Section be used as a design handbook; rather, engineering judgement must be employed..."

What, specifically, is the AI's objection? If it's that ASME has not "endorsed" WRC 429, it should be noted that ASME has a general policy of not "endorsing" specific calculation procedures - and only provided minimum requirements where and when required. I have used other FE-based methodologies that will likely never be incorporated into the Code, but I can demonstrate the requirement of U-2(g).
 