eltelme
Structural
- May 6, 2009
- 4
I am working as a civil engineer in oil industry.
I have used a culvert so that the pipe rack (at 1 meter elevation) will cross the road. The road will go up to culvert elevation (2.35m) and then down. I have not used any approach slab before and after the culvert, so is it wrong?
Is the road slope acceptable?
Thanks and regards,
I have used a culvert so that the pipe rack (at 1 meter elevation) will cross the road. The road will go up to culvert elevation (2.35m) and then down. I have not used any approach slab before and after the culvert, so is it wrong?
Is the road slope acceptable?
Thanks and regards,