bpiermat
Structural
- Mar 7, 2006
- 44
So I have a post-installed anchor connection. All concrete is unreinforced, but members are large. My question is: Can I ignore Pry-out in Appendix D or can I modify the equation in Appendix D.
Here is my specific case: The Slab to Wall Connection, the Slab is 8' deep and the Wall is 3' Deep. If the dowel is post-installed in the wall at the center of the slab and then the slab is placed after the dowel is installed, should my pryout effective width be equal to 8' = 1.5 Hef? Or does this condition not even apply at all?
Thanks in advance!
Here is my specific case: The Slab to Wall Connection, the Slab is 8' deep and the Wall is 3' Deep. If the dowel is post-installed in the wall at the center of the slab and then the slab is placed after the dowel is installed, should my pryout effective width be equal to 8' = 1.5 Hef? Or does this condition not even apply at all?
Thanks in advance!