Gentlemen,
At section 7 paragraph 7.5.5 only tolerances for horizontal slope is stated even if with or without ring wall and concrete slab was installed. My query, as to my attachment my level check point interval is 5m radius at 3m apart this is correct or not? if its correct where i can find the relevant document that consider in this matter.
Suggestion, Comments, Violence reaction etc. is highly appreciated.
Thank you in advanced . .. . ..
At section 7 paragraph 7.5.5 only tolerances for horizontal slope is stated even if with or without ring wall and concrete slab was installed. My query, as to my attachment my level check point interval is 5m radius at 3m apart this is correct or not? if its correct where i can find the relevant document that consider in this matter.