i have another question regarding a hole location call out based on the feature control frame.
Based on the attached pdf i would like to confirm what is being asked for in terms of the hole in question.
It has a FCF of .005 M to datum D (area to the left when looking at the part from side), Datum G (regardless of feature size, which is the hole and Datum E (the line).
Datum G has a callout to be within .016 of datum D, E and F. i see the BASIC dimensions related to this location.
However for the hole in question, i see the BASIC dimensions off of Datum G but not Datum E.
So the question i have is, do i incorporate the values from Datum E (calculated values) or do i just focus on the location of the hole in reference to Datum G (since datum G already is based off Datum E)?
Greatly appreciate the help, thank you
i have another question regarding a hole location call out based on the feature control frame.
Based on the attached pdf i would like to confirm what is being asked for in terms of the hole in question.
It has a FCF of .005 M to datum D (area to the left when looking at the part from side), Datum G (regardless of feature size, which is the hole and Datum E (the line).
Datum G has a callout to be within .016 of datum D, E and F. i see the BASIC dimensions related to this location.
However for the hole in question, i see the BASIC dimensions off of Datum G but not Datum E.
So the question i have is, do i incorporate the values from Datum E (calculated values) or do i just focus on the location of the hole in reference to Datum G (since datum G already is based off Datum E)?