mfstructural
Structural
- Feb 1, 2009
- 230
Hey all,
I have a situation where we are adding a mezzanine to an existing warehouse building. The warehouse is about 30' high and the mezzanine will be about 10' off the slab. I am working with another structural engineer and architect on this project.
The mezzanine is planned to be 100' x 40', with 3 columns per frame. There will be 8 frames spaced at about 12'.
My issue is that they want to anchor the column base plates directly to the slab on grade which is 6" thick. I had suggested providing footings but they claim anchoring to the slab is sufficient. They are also proposing to have the columns designed as flag poles and this would be the lateral system...no bracing or moment frames. The building is in northern Michigan so not a high seismic area but I'm not sure I like the idea of anchoring directly to an existing slab.
In the past I've always provided footings. I suppose if you show the anchors are sufficient with a sufficient amount of clearance between the bottom of slab and end of anchor hole and also that the slab can resist the moment (assuming no reinforcement) then this would be feasible. The mezzanine will be used as an office so it's 50 psf LL.
We are planning on spanning 2x12's or wood trusses between the frames so the DL will be low. I'm not sure if this will be feasible; the architect is looking into fire protection requirements.
Any thoughts or has anyone ever anchored to an existing slab on grade?
I have a situation where we are adding a mezzanine to an existing warehouse building. The warehouse is about 30' high and the mezzanine will be about 10' off the slab. I am working with another structural engineer and architect on this project.
The mezzanine is planned to be 100' x 40', with 3 columns per frame. There will be 8 frames spaced at about 12'.
My issue is that they want to anchor the column base plates directly to the slab on grade which is 6" thick. I had suggested providing footings but they claim anchoring to the slab is sufficient. They are also proposing to have the columns designed as flag poles and this would be the lateral system...no bracing or moment frames. The building is in northern Michigan so not a high seismic area but I'm not sure I like the idea of anchoring directly to an existing slab.
In the past I've always provided footings. I suppose if you show the anchors are sufficient with a sufficient amount of clearance between the bottom of slab and end of anchor hole and also that the slab can resist the moment (assuming no reinforcement) then this would be feasible. The mezzanine will be used as an office so it's 50 psf LL.
We are planning on spanning 2x12's or wood trusses between the frames so the DL will be low. I'm not sure if this will be feasible; the architect is looking into fire protection requirements.
Any thoughts or has anyone ever anchored to an existing slab on grade?