FHRebuildEng
Civil/Environmental
I am planning some temparory works to repair a bridge.
Part of these works require a 180t crane and there is an 11KVA cable running though the middle of the site.
The cable owner has stated that we are not to damage it (no ....), however has left it up to us to do this and will not provide any useful info on allowable stress on the cable.
I plan to protect the cable using compacted earth.
So I need to know what is the maxium allowable settlement and pressure on the cable.
Further more what else do i need to know/consider?
regards
Part of these works require a 180t crane and there is an 11KVA cable running though the middle of the site.
The cable owner has stated that we are not to damage it (no ....), however has left it up to us to do this and will not provide any useful info on allowable stress on the cable.
I plan to protect the cable using compacted earth.
So I need to know what is the maxium allowable settlement and pressure on the cable.
Further more what else do i need to know/consider?
regards