nli2
Chemical
- Jan 27, 2006
- 9
A air tank (vertical) located in the discharge line of the existing 2 rotary screw air compressors: (1) to remove the possible contaminant. (2) provide buffer time and smooth the compressor operation.
we shall install a new compressor with same capacity as existing cmprs. Idea is try to share the existing air tank for the new compressor.
I know that there are two ways for the air tank sizing.
(1) estimating the required receiver size is based on compressed volume.
V= (Q *Pa)/ (Pi+Pa)
where: V= receiver size (ft3)
Q=compressor output (cfm)
Pa= standard atmospheric pressure (psi)
Pi= Compressed pressure (psi)
(2) based on a variable demand situation.
V= t (Qout-Qin)x Pa/ (P1-P2)
Where Qout:flow rate out; cfm.
Qin: flow rate in; cfm.
V: receiver size (ft3)
t: time to charge or discharge,min
Pa: atmosphere pressure, psi
P1: Initial working pressure,psi.
P2: Final working pressure, psi.
Question is for way (2):
Any normal practice or experience for formula 2 sizing scenarios in plant?
I can imagine that some,
plant has increased air demand for several minutes at some scenarios, the initial header pressure 7 barg, and the header pressure can not drop to ?? ...
or utility failure, compressor trips, have to provide some instrument air buffer time for emergency shut down etc. ...
thanks,
nli2
we shall install a new compressor with same capacity as existing cmprs. Idea is try to share the existing air tank for the new compressor.
I know that there are two ways for the air tank sizing.
(1) estimating the required receiver size is based on compressed volume.
V= (Q *Pa)/ (Pi+Pa)
where: V= receiver size (ft3)
Q=compressor output (cfm)
Pa= standard atmospheric pressure (psi)
Pi= Compressed pressure (psi)
(2) based on a variable demand situation.
V= t (Qout-Qin)x Pa/ (P1-P2)
Where Qout:flow rate out; cfm.
Qin: flow rate in; cfm.
V: receiver size (ft3)
t: time to charge or discharge,min
Pa: atmosphere pressure, psi
P1: Initial working pressure,psi.
P2: Final working pressure, psi.
Question is for way (2):
Any normal practice or experience for formula 2 sizing scenarios in plant?
I can imagine that some,
plant has increased air demand for several minutes at some scenarios, the initial header pressure 7 barg, and the header pressure can not drop to ?? ...
or utility failure, compressor trips, have to provide some instrument air buffer time for emergency shut down etc. ...
thanks,
nli2