I'm in the process of designing some pilasters with fairly large loads and am planning to design supplemental reinforcing to prevent concrete breakout. The problem that is arising for me is that pryout is controlling shear failure.
My interpretation of the code is that supplemental reinf. is for concrete breakout only, exclusive of pryout, but am i being to restrictive on my design?
In appears to me, that Pryout is a similar failure to Tension Breakout, so if i properly design supplemental tension reinf. can i assume pryout will not control the design?
Any thoughts or interpretations on this matter would be great.
My interpretation of the code is that supplemental reinf. is for concrete breakout only, exclusive of pryout, but am i being to restrictive on my design?
In appears to me, that Pryout is a similar failure to Tension Breakout, so if i properly design supplemental tension reinf. can i assume pryout will not control the design?
Any thoughts or interpretations on this matter would be great.