Prestressed Guy
Structural
- May 11, 2007
- 390
When performing a 3D modal Analysis with one of the many software packages, I have had different responses from plan reviews within the same building departments. Most of the time my projects are approved without comment but other times….
I currently have a single family residence that is to be built with concrete bearing walls (ICF) and SJI floor joists with composite concrete floor slabs. The structure is on a view site and is all window towards the view. Because of this it is a torsional irregular type 1a building. Even so, it is extremely stiff with very little stress in the walls. The plans reviewer has requested additional information 4 times. It seems that no matter what I send it doesn’t seem to answer her questions. I am temped to just do a full output dump to a PDF file and send it to her but that would run to approximately 20,000 pages. This building is your proverbial concrete sh__-house. It seams that the reviewer works mostly on wood stick framed houses and is trying to perform a full hand check on my calculations. She is asking for simplistic answers to complex question.
So what do you normally submit in the way of a calculation package?
I currently have a single family residence that is to be built with concrete bearing walls (ICF) and SJI floor joists with composite concrete floor slabs. The structure is on a view site and is all window towards the view. Because of this it is a torsional irregular type 1a building. Even so, it is extremely stiff with very little stress in the walls. The plans reviewer has requested additional information 4 times. It seems that no matter what I send it doesn’t seem to answer her questions. I am temped to just do a full output dump to a PDF file and send it to her but that would run to approximately 20,000 pages. This building is your proverbial concrete sh__-house. It seams that the reviewer works mostly on wood stick framed houses and is trying to perform a full hand check on my calculations. She is asking for simplistic answers to complex question.
So what do you normally submit in the way of a calculation package?