ali07
Structural
- Dec 6, 2007
- 171
Hi Guys,
What are the consequences of a well designed 30 MPa parking garage concrete slab (exposed condition) vs. 35MPa required as per code. As the slab in question is low by 5 MPa, as per engineering judgement, is it necessary to demolish the slab or are there any means to improve the durability/permability of the concrete to reduce the anticipated cracking due to freeze/thaw.
What are the consequences of a well designed 30 MPa parking garage concrete slab (exposed condition) vs. 35MPa required as per code. As the slab in question is low by 5 MPa, as per engineering judgement, is it necessary to demolish the slab or are there any means to improve the durability/permability of the concrete to reduce the anticipated cracking due to freeze/thaw.