HawkBrazil
Electrical
- Aug 23, 2003
- 8
Dear Friends
I have a problem today in Brazil, related with a 2 UPS's and we need to make a transfer of load between that equipments in case of fail of one.
In a first moment most of us don't can see any problem, but when you discover of that 2 UPS's are double conversion - not true on line - the problem appears.
Anyone here know any solution for this ? The sinus are not at the same position at the entrance of STS, then if the transfer happens, we loose the load.
TKS for all.
Wagner Freitas
WR Freitas Consulting Engineers
Rio de Janeiro - Brazil
I have a problem today in Brazil, related with a 2 UPS's and we need to make a transfer of load between that equipments in case of fail of one.
In a first moment most of us don't can see any problem, but when you discover of that 2 UPS's are double conversion - not true on line - the problem appears.
Anyone here know any solution for this ? The sinus are not at the same position at the entrance of STS, then if the transfer happens, we loose the load.
TKS for all.
Wagner Freitas
WR Freitas Consulting Engineers
Rio de Janeiro - Brazil